1 |
DEVELOPMENT OF SITE AT THE CONFLUENCE OF M-1 & RING ROAD. |
|
75% |
56.540 |
2 |
WIDENING & IMPROVEMENT OF EXISTING G.T ROAD FROM ZAKORI BRIDGE TO SURAI PUL BRIDGE PESHAWAR (SECTION-1) AND IMPROVEMENT OF EXISTING JAMRUD ROAD FROM SHAMA CHOWK TO ADMINISTRATIVE BOUNDARY. |
Completed. Except asphaltic concrete on a portion measuring 450 meter due to Status quo obtained by Pakistan Railways. |
98 |
481.949 |
3 |
CONSTRUCTION OF HAYATABAD DETOUR INCLUDING SERVICE ROAD (ONE SIDE), TOLL PLAZA AND 3-NO. BRIDGES PH-I (02-KM). |
Road work …. 75%
Bridge work ….60%.
Status quo obtained by locals.
|
70% |
489.272 |
4 |
REHABILITATION/IMPROVEMENT OF PAJJAGI ROAD FROM BACHA KHAN CHOWK TO BACHA KHAN MARKAZ BASHIR ABAD |
|
60% |
66.129 |
5 |
REHABILITATION/IMPT: OF ABBASEEN FLOOR MILL DALAZAK ROAD TO LINK ROAD ARBAB NIAZ STADIUM, PESHAWAR |
|
80% |
35.913 |
6 |
GROUP OF ROADS |
a. Rehab: & Impt: of Police Chowki Road
b. Ijaz Abad road upto Sir Syed School Chowk
c. Afridi Ghari Ring Road to Khyber Eye Foundation
d. Farid Abad to Ijaz Abad and side drain upto UC-II, Peshawar
e. Ishrat Cinema road to Sir Syed School chowk
|
40% |
|
7 |
IMPT: OF SHAMI ROAD FROM BACHA KHAN CHOWK TO FEDERAL LODGES |
|
35% |
48.156 |
8 |
REHAB: & IMPT: OF AFGHAN COLONY CANAL TO FAQIR ABAD POLICE STATION VIA ASHRAFIA COLONY, PESHAWAR |
|
65% |
59.76 |
9 |
REHAB: & IMPT: OF G.T ROAD TO KABUL RIVER CANAL VIA GOVT. COLLEGE, PESHAWAR |
|
50% |
57.029 |
10 |
PC-II FOR CONSTRUCTION OF ELEVATED U-TURNS ON JAMRUD ROAD |
Matter has been taken up with NLC as suggested in minutes of the DDWP. |
0% |
5.000 |
11 |
PC-II FOR BEAUTIFICATION OF HAYATABAD |
|
Consultant appointed. |
5.400 |
12 |
PC-II FOR CONSTRUCTION OF SERVICE ROADS ALONG RING ROAD |
Combined evaluated report was approved by DCSC in its meeting held on 04.11.2015. The award of contract for consultancy is under process. |
award of contract for consultancy is under process |
24.00 |
13 |
CONSTRUCTION OF RETAINING WALL AND ROAD ALONG NARAI KHAWAR AT TAJ ABAD |
|
50% |
67.002 |
14 |
OUTFALL DRAIN FROM JAMEEL CHOWK TO AFRIDI GHARI |
PC-I approved. Contract being awarded. |
Contract being awarded |
59.59 |
15 |
CONSTRUCTION OF JANAZGAH AND PLAYGROUND IN PK-5 |
|
|
4.500 |
16 |
REHABILITATION OF DRAIN AND CONSTRUCTION OF FOOTPATH ALONG MAIN ROAD AT PHASE-V HAYATABAD |
|
50% |
67.002 |
17 |
CONSTRUCTION OF ROADS |
a. Road Opposite Akbar Town, Peshawar.
b. Gur Mandi Road and construction of drain Hashtnagri, Peshawar
c. Nasir Bagh Road to Madina street end Murad Abad, Peshawar
|
10% |
18.99 |
18 |
DEVELOPMENT OF GREEN BELT ALONG RAILWAY LINE JAMRUD ROAD FROM PHASE-V ENTRY HAYATABAD TO ADMINISTRATIVE BOUNDARY KARKHANO MARKET, PESHAWAR |
Work order issued work stopped due to status quo obtained by Pakistan Railways. |
Work order stopped |
52.37 |
19 |
SHIFTING OF PESCO HT & LT LINES FROM TAMBOWANO MOR TO PDA NURSERY PHASE-III CHOWK LEFT & RIGH BOTH SIDES ON JAMRUD ROAD |
|
0% |
32.436 |
20 |
REMODELING OF GORA QABRISTAN CHECK POST |
|
Ongoing |
26.000 |
21 |
REHABILITATION/IMPT: OF INTER COLLEGE ROAD UPTO CHARSADDA ROAD TO PESHAWAR |
a. Rehabilitation/impt: of inter college road upto Charsadda road to Peshawar
b. Rehabilitation/impt: of Wazir Colony Road, Peshawar
|
43% |
26.436 |
22 |
SARDAR AHMAD JAN COLONY STREET. NO. 1 FROM RING ROAD TO AFGHAN COLONY ROAD, PESHAWAR |
a. Sardar Ahmad Jan Colony Street. No. 1 from Ring Road to Afghan Colony Road, Peshawar
b. Road from Ring Road to Jehangir Hujra, Peshawar
c. Faisal Colony to G.T Road, Peshawar
d. Gulshan Colony to G.T Road, Peshawar
|
Contract being awarded to NLC. |
16.841 |
23 |
REHABILITATION/IMPT: OF ROAD FROM GUL ABAD CHOWK TO FAISAL COLONY CHOWK, PESHAWAR |
|
80% |
23.006 |
24 |
UP-GRADATION OF KABUL RIVER CANAL ROAD VIA AFRIDI GHARI TO RING ROAD |
|
65% |
20.882 |
25 |
UP-GRADATION OF KABUL RIVER CANAL ROAD VIA RADIO PAKISTAN TRANSMISSION LINE TO RING ROAD. |
|
85% |
49.082 |
26 |
REHABILITATION / IMPROVEMENT OF DALAZAK ROAD FROM BACHA KHAN CHOWK TO K.R.C YOUSAF ABAD PESHAWAR. |
|
15% |
59.955 |
27 |
G.T ROAD VIA CITY TOWN TO MORTOR WAY PESHAWAR |
|
85% |
21.325 |
28 |
REHABILITATION / IMPROVEMENT OF DALAZAK ROAD FROM YOUSAF ABAD (KRC) TO RING ROAD PESHAWAR. |
|
5% |
59.599 |
29 |
RING ROAD TO JOE SHEIKH VIA LATIF ABAD PESHAWAR |
|
Tender received. Contract being awarded |
17.93 |
30 |
UP-GRADATION OF ROAD BACHA KHAN COLONY TO RING ROAD PESHAWAR. |
|
Tender received. Contract being awarded |
22.799 |
31 |
UP-GRADATION OF ROAD SARDAR AHAMD JAN COLONY TO MOHMAND CNG RING ROAD. |
|
Tender received. Contract being awarded |
14.727 |
32 |
UP-GRADATION OF ROAD RING ROAD VIA JEHANGIRABAD NO.2 ALONG WITH JOE SHEIKH CANAL TO GARHI BALOCH. |
|
Tender received. Contract being awarded |
59.358 |
33 |
BAB-E-PESHAWAR FLYOVER |
|
77% |
1772.492 |
34 |
PESHAWAR UPLIFT PROGRAM |
|
Progress |
2980.262 |
35 |
PROVISION OF LED ROAD LIGHTS FROM ZAKORI BRIDGE TO ADMINISTRATIVE BOUNDARY |
|
PC-I approved. Tenders invited. |
139.00 |
36 |
NORTHERN SECTION OF RING ROAD (MISSING LINK) PESHAWAR FROM PAJJAGI ROAD TO WARSAK ROAD |
Land for Warsak road intersection is being acquired.
|
Ongoing |
6989.00 |
37 |
UP-GRADATION OF RADIAL ROADS LEADING TO RING ROAD. |
11 schemes.
Progress
06 schemes completed by 90%
01 scheme completed by 5%.
04 schemes, NIT invited. (16.11.2015).
Details are placed at Annexure-II.
|
90% |
400 |
38 |
NORTHERN SECTION OF RING ROAD FROM WARSAK ROAD TO NASIR BAGH ROAD INCLUDING LAND COST. |
PC-I for land acquisition approved @ Rs.2827.00 (M). Process in hand.
|
PC-I for land acquisition approved |
8500 |
39 |
BEAUTIFICATION OF PESHAWAR FROM ZAKORI BRIDGE TO SURAI PUL. |
|
60% |
103.533 |
40 |
BEAUTIFICATION AND UPLIFT OF MUNICIPAL AREAS ON G.T ROAD FROM PABBI TO JHANGIRA |
Design approved. Cost estimation in progress.
|
Cost estimation in progress. |
400 |
41 |
UP-LIFT OF REGI MODEL TOWN (RMT) INCLUDING PROVISION OF UTILITIES AND OTHER INFRASTRUCTURES (PHASE-I) |
Progress Sui gas and electrification work in progress. Additional funds of Rs.800.00 million over & above the CFY ADP 2015-16 provision are required.
|
work in progress |
1000.00 |
42 |
CONSTRUCTION OF HAYATABAD DETOUR INCLUDING SERVICE ROAD AND BRIDGE. |
Progress
Road Work 70%
Bridge Work 50%
Work partially suspended owing status quo issued by the Court.
Summary moved for land compensation (Phase-II) to the Honorable C.M
|
70% |
489.272 |
43 |
AMALGAMATION OF JAMRUD ROAD WITH SERVICE ROAD FROM TAMBWANO MORH TO HAYATABAD. |
Progress Payment of Rs.25.00 (M) made to PESCO for shifting of HT/LT lines. Consultant appointed. Work on design and estimation in progress.
|
Ongoing |
NaN |