S# Title Detail % Completed Project Cost
1 BAB-E-PESHAWAR FLYOVER Completed by 85%. 1772.492
2 PESHAWAR UPLIFT PROGRAM 27 schemes. Progress 04 schemes completed by 100% 03 schemes completed by 80% 04 schemes completed by 50 – 60% 14 schemes completed by 30 - 40 % 02 schemes contract being awarded Additional funds of Rs.713.935 (M) required. 27 schemes in progress 2980.262
3 BEAUTIFICATION OF PESHAWAR FROM ZAKORI BRIDGE TO SURAI PUL. Progress 60% (Feb 2015) 60% 103.533
4 BEAUTIFICATION AND UPLIFT OF MUNICIPAL AREAS ON G.T ROAD FROM PABBI TO JHANGIRA Design approved. Cost estimation in progress. Cost estimation in progress. 400.00
5 FEASIBILITY OF GENERAL BUS STAND IN PESHAWAR MOU for design & build signed with NLC. Presentation to Honorable C.M for final approval of design in 2nd week of December, 2015. pending 100.00
6 PROVISION OF LED ROAD LIGHTS FROM ZAKORI BRIDGE TO ADMINISTRATIVE BOUNDARY Tenders opening 139.00
7 CONSTRUCTION OF PRE-FABRICATED ELEVATED U-TURNS/DEDICATED U-TURNS IN PESHAWAR Discussed with NLC/ consultant. Because of widening of Jamrud Road, no space will be available. no space will be available. 1000.00
8 NORTHERN SECTION OF RING ROAD (MISSING LINK) PESHAWAR FROM PAJJAGI ROAD TO WARSAK ROAD Land for Warsak road intersection is being acquired. Contracts awarded. Pajjagi Road Flyover (10 months) Road Work (12 months) iii. Budni Nullah Bridge (06 months) Contracts awarded 6989.00
9 UP-GRADATION OF RADIAL ROADS LEADING TO RING ROAD. 11 schemes. Progress 06 schemes completed by 90% 01 scheme completed by 5%. 04 schemes, Bids received. Contract being awarded.. in Progress 400.00
10 NORTHERN SECTION OF RING ROAD FROM WARSAK ROAD TO NASIR BAGH ROAD INCLUDING LAND COST PC-I for land acquisition approved @ Rs.2827.00 (M) . Process in hand. PC-I for land acquisition approved 8500.00
11 CONSTRUCTION OF SHINGLED SERVICE ROAD FOR RING ROAD FROM HAYATABAD TO CHARSADDA ROAD Summary forwarded to Honorable C.M for revision of cost /change of scope @ Rs.1871.5 (M). Summary forwarded to CM 200
12 UP-LIFT OF REGI MODEL TOWN (RMT) INCLUDING PROVISION OF UTILITIES AND OTHER INFRASTRUCTURES (PHASE-I) Progress Sui gas and electrification work in progress. Additional funds of Rs.800.00 million over & above the CFY ADP 2015-16 provision are required. Sui gas and electrification work in progress 1000.00
13 SAFE CITY HAYATABAD PROJECT. Revised PC-I has been approved by PDWP conditionally. The requisite action is being taken by PDA prior to award of contracts. Revised PC-I has been approved 400
14 CONSTRUCTION OF HAYATABAD DETOUR INCLUDING SERVICE ROAD AND BRIDGE. Progress Road Work 70% Bridge Work 50% Work partially suspended owing status quo issued by the Court. Summary moved for land compensation (Phase-II) to the Honorable C.M 70% 489.272
15 AMALGAMATION OF JAMRUD ROAD WITH SERVICE ROAD FROM TAMBWANO MORH TO HAYATABAD. Progress Payment of Rs.25.00 (M) made to PESCO for shifting of HT/LT lines. Consultant appointed. Work on design and estimation in progress. Ongoing NaN